Check List for The 3D Galaxy Model Review:

1.            The comments of model review are closed.
 
2.            Inter discipline model review is conducted and comments of the same are incorporated.
 
3.            All Equipment checked to IFC Vendor information.
 
4.            All piping modeled including piping below 2”
 
5.            All Pipe supports are modeled and checked
 
6.            All Stress comment incorporated and checked
 
7.            All Steel Structures are completed and checked with respect to IFC drawings
 
8.            All Buildings are completed and checked with respect to IFC drawings
 
9.            All Foundations are completed and checked with respect to IFC drawings
 
10.         All Online, Off-line and equipment mounted Instruments are completed and checked with respect to approved vendor drawings.
 
11.         All Telecom items including CCTV’s, PAGA speakers are shown and checked
 
12.         All Lighting fixtures are completed and checked.
 
13.         All electrical panels / Distribution Boards are completed and checked.
 
14.         All Fire & Gas Equipment is completed and checked
 
15.         All U/G facilities completed and checked.
 
16.         Any exclusion from a model review is incorporated and checked.
 
17.         All Utility Stations are identified, located and checked for the maximum length of hose with proper access.
 
18.         All Safety showers and eye baths are identified, located and checked with proper access.
 
19.         Location of mobile and portable /manual firefighting equipment are shown and checked.
 
20.         All Sample connections are identified and modeled and checked for proper access.
 
21.         The minor access platforms, if any are located and checked for proper access.
 
22.         The offline instruments including analyzer enclosures/panels etc. are modeled at proper locations and checked.
 
23.         The fire and gas detectors are shown and location of each is checked by HSE for function and by piping for obstruction.
 
24.         The cable routing inside the building is complete and checked so that it is not obstructing any movement of crane or walkways.
 
25.         All the instrument stands and supports are checked so that they are not obstructing the walkways on the platforms especially in case of platforms located on vertical vessels and columns.
 
26.         Location of junction boxes is checked so that they are not obstructing the walkways.
 
27.         A junction boxes/fire box is modeled with volume for door opening and does not enter into the hard standing/access areas located for crane/walkways, etc.
 
28.         Cable conduits are checked so that they are not coming out in the middle of the road/ walkways.
 
29.         Ensure that arrangement of small bore piping has been done in such a way that the pipe support is provided to prevent the breakage due to vibration.
 
30.         Ensure purging connection is provided at the dead end of flare header.
 
31.         Ensure that cooling water lines branch off from the header from top.
 
32.         Ensure that there are no valves installed with the stem pointing below the horizontal plane in downward direction.
 
33.         Ensure that the vents from an analyzer house/cabinet are located and routed to atmosphere at safe height from grade.
 
34.         The vents of seal chambers of reciprocating compressors are properly routed and supported.
 
35.         Unloading and storage of chemicals and additives is reviewed for any environmental impact.
 
36.         Vendor trim piping around equipment is put in the model and checked.
 
37.         Ensure Toe plate is modeled properly at platform opening.
 
38.         Check that the Siren/safety alarm system is installed at top of highest building and at the centre of plant area.
 
39.         The proper lighting poles and fixtures etc. are shown and checked.
 
40.         The safety equipment like wind socks, breathing apparatus are strategically located as per escape and safety equipment layout.
 
41.         The routing of branch cable trays to the instrument and support for the same is properly shown and checked.
 
42.         The parking area, traffic barriers, boulders, etc. as applicable is modeled and checked.
 
43.         Steam tracing manifolds and steam jacketing details are shown in model and checked.
 
44.         All design change notices (DCNs) are taken care with respect to completeness.

 